Dismount
of old system of wood gates in Puerto Madero. Dock1/Darsena Sud,
extracting of 6 gates of 100 tons of weight each one built in 1889.
|
 |
|
|
|
|
|
| |
Assembly
of the turn system and two fixed plates of the Puente de la Mujer
(Calatrava Architect) with use of G/F "HERCULES" in Dock3
of Puerto Madero. |
 |
|
|
|
|
|
| |
Demolition
and underground adaptation of Refrigeration sea inlet 1 and 3 of Central
Termica Dock Sud. |
 |
|
|
|
|
|
| |
Off-Shore
diving services in connection with the installation of pipeline for
the Gasoducto Cruz del Sur between Argentina and the Rep. Oriental
del Uruguay, in Rio de La Plata crossing. |
 |
|
|
|
|
|
| |
Providing
of Pontoons and tug for the transporting of pipeline for the Gasoducto
Cruz del Sur between Argentina and the Rep. Oriental del Uruguay,
in Rio de La Plata crossing. |
 |
|
|
|
|
|
| |
Assembly
grids inlet sea, recovering and repairs anchoring lines and recovering
of lost charge,
are some of the done works developers. |
 |
|
|
|
|
|
| |
Cleaning
and Inspection of the aspiration pipe of water of 40 mts. of longitude
to a depth of 24 mts. of the Plant Celulosa Alto Paraná, in
Misiones Rep. Argentina. For Alto Parana S.A.
|
 |
|
|
|
|
|
| |
Cleaning,
repairs and change grids of the inlet refrigeration water Hydroelectric
Futaleufu Dam, with 48 mts.depth . In the Lake Futalaufquen of the
Pcia. of Chubut. For Aluar CORP.
|
 |
|
|
|
|
|
| |
Underwater
Survey sinking B/P "CONARPESA V", casualty in proximities
of Camarones Bay in a depth of 29 mts. To carried out the inspection
with evaluation of damages, video filming and photographs. |
 |
|
|
|
|
|
| |
Reparation
and reinstalation of Barge Defensa de la Pila 250 of Bridge Gral.
Justo Jose de Urquiza of Complex Zarate/Brazo Largo. River Parana
Guazu. |
 |
|
|
|
|
|
| |
Underwater
repair of gas pipeline Cruz del Sur, detection and measurement of
damage place, transportation of equipment and preparing for montage
of habitat welding (welding realized by divers of Global Company),
complete protection and consolidation of a pipe, repairing of progressive
12.4 of crossing Rio de la Plata.
|
 |
|
|
|
|
|
| |
Whole
repairing and reinstallation of Tower Pump W-35 in Rio de la Plata,
property of Distillers Shell C.A.P.S.A.
|
 |
|
|
|
|
| |
Reinstallation
of fixed arms system of Corbeta "ARA URUGUAY" in Dock 4
of Puerto Madero.
|
 |
|
|
|
|
|
| |
Integral
survey and mensuration of current speed of water of the pipeline Mesopotámico
in crossing Parana River, Aldea Brasilera (under water crossing) for
Transportadora de Gas del Norte
|
|
|
|
|
|
|
| |
Integral
submarine survey and potentials mensuration of the anchorages system
of the gas-pipeline San Martin in Costa Norte Estrecho de Magallanes
(submarine crossing) for Transportadora de Gas del Sur.
|
|
|
|
|
|
|
| |
Installation
of metallic filters plates for sealing of piles in the New Port San
Nicolás berth. For account of Pilotes TREVI S.A.
|
|
|
|
|
|
|
| |
Removal
with uderwater blastings and extraction of the basements of the old
bridge for the crossing the Arroyo Potrero Stream in the .Prov. Nº
1. Customer: Marcalba S.A
|
|
|
|
|
|
|
| |
Transport
and mounting of two fire towers of 18 mts. of height and 5 tons
weight each one, in the propane Dock Sud Customer: CA Group. S.A
|
|
|
|
|
|
|
| |
Nailed
with flogging hammer of metallic piles-cover for the construction
of a new two dolphins of mooring of the Casino Puerto Madero, Dársena
Sud Puerto de Buenos Aires. Client: DIPRONOR S.A.
|
|
|
|
|
|
|
| |
Rescue
with Floating Crane of an overturned caterpillar mounted crane on
the Pontoon "29", over the deck with fall risk in to the
Dock South access Channel, weight of the rescued crane, 70 tons.
Client: DYOPSA S.A.
|
|
|
|
|
|
|
| |
Removal
and extraction of remains of the former La Salada Bridge, General
Belgrano Railroad, 24 wooden piles and their concrete basis were
extracted buried up to 6 mts. in the channel, also the profiles
were extracted who conformed the bridge plate, liberating the water
laying. Client: Comite Ejecutor de la Cuenca Matanza-Riachuelo
|
|
|
|
|
|
|
| |
Dredged
and post-trenching of pipeline tract San Martin II in the crossing
of the River Chubut, Dolavon, Chubut Province. One carries out a
dredged by suction, with the Modular Dredge "MARTIRIO"
and attendance with divers of interferences liberation, achieving
the burial under the layer of a ø 24"pipeline. Client:
SKANSKA S.A.
|
|
|
|
|